Dam removal timeline

From Beam Reach Wiki
Revision as of 00:19, 17 April 2009 by WikiSysop (Talk | contribs)

Jump to: navigation, search

Key contacts

  • Bill Laitner, Olympic National Park (ONP) Superintendent
  • Barb Maynes, ONP press/news releases (360) 565-3005

Projected dates and deadlines

  • 02/2011: Deadline for Watts/DelHur to complete EWF (unless deadline is adjusted!)
  • 02/2010: Anticipated complestion of EWF; 3/2009 newsletter stated "Construction of the EWF is approximately one year ahead of schedule, with completion anticipated in February 2010."
  • 11/2009: PAWTP is scheduled for completion "late" in fall, 2009 (ref)
  • 02/2008: NPS expected to issue a Notice to Proceed (on EWF) to Watts/DelHur
  • 01/2008: award of construction management contract for EWF)
  • 10/2007: NPS expected to issue a Notice to Proceed (on PAWTP) to Watts/Korsmo

Recent events (confirmed to have occurred)

  • 12/12/2007: contract awarded for the Elwha Water Facilities (EWF); $69,649,900 to Watts/DelHur
  • 09/07/2007: contract awarded for construction of the Port Angeles Water Treatment Plant (PAWTP); $24,482,750 to Watts/Korsmo