Difference between revisions of "Dam removal timeline"
From Beam Reach Wiki
(New page: == Key contacts == * Bill Laitner, Olympic National Park (ONP) Superintendent * Barb Maynes, ONP press/news releases (360) 565-3005 == Projected dates and deadlines == * 02/2011: Deadl...) |
|||
Line 7: | Line 7: | ||
* 02/2011: Deadline for Watts/DelHur to complete EWF (unless deadline is adjusted!) | * 02/2011: Deadline for Watts/DelHur to complete EWF (unless deadline is adjusted!) | ||
+ | * 02/2010: Anticipated complestion of EWF; [http://www.nps.gov/olym/parknews/park-newsletter-march-2009.htm 3/2009 newsletter] stated "Construction of the EWF is approximately one year ahead of schedule, with completion anticipated in February 2010." | ||
+ | * 11/2009: PAWTP is scheduled for completion "late" in fall, 2009 ([http://www.nps.gov/olym/parknews/park-newsletter-march-2009.htm ref]) | ||
* 02/2008: NPS expected to issue a Notice to Proceed (on EWF) to Watts/DelHur | * 02/2008: NPS expected to issue a Notice to Proceed (on EWF) to Watts/DelHur | ||
* 01/2008: award of construction management contract for EWF) | * 01/2008: award of construction management contract for EWF) |
Revision as of 01:19, 17 April 2009
Key contacts
- Bill Laitner, Olympic National Park (ONP) Superintendent
- Barb Maynes, ONP press/news releases (360) 565-3005
Projected dates and deadlines
- 02/2011: Deadline for Watts/DelHur to complete EWF (unless deadline is adjusted!)
- 02/2010: Anticipated complestion of EWF; 3/2009 newsletter stated "Construction of the EWF is approximately one year ahead of schedule, with completion anticipated in February 2010."
- 11/2009: PAWTP is scheduled for completion "late" in fall, 2009 (ref)
- 02/2008: NPS expected to issue a Notice to Proceed (on EWF) to Watts/DelHur
- 01/2008: award of construction management contract for EWF)
- 10/2007: NPS expected to issue a Notice to Proceed (on PAWTP) to Watts/Korsmo
Recent events (confirmed to have occurred)
- 12/12/2007: contract awarded for the Elwha Water Facilities (EWF); $69,649,900 to Watts/DelHur
- 09/07/2007: contract awarded for construction of the Port Angeles Water Treatment Plant (PAWTP); $24,482,750 to Watts/Korsmo