Difference between revisions of "Dam removal timeline"
From Beam Reach Wiki
(New page: == Key contacts == * Bill Laitner, Olympic National Park (ONP) Superintendent * Barb Maynes, ONP press/news releases (360) 565-3005 == Projected dates and deadlines == * 02/2011: Deadl...) |
(No difference)
|
Revision as of 00:03, 17 April 2009
Key contacts
- Bill Laitner, Olympic National Park (ONP) Superintendent
- Barb Maynes, ONP press/news releases (360) 565-3005
Projected dates and deadlines
- 02/2011: Deadline for Watts/DelHur to complete EWF (unless deadline is adjusted!)
- 02/2008: NPS expected to issue a Notice to Proceed (on EWF) to Watts/DelHur
- 01/2008: award of construction management contract for EWF)
- 10/2007: NPS expected to issue a Notice to Proceed (on PAWTP) to Watts/Korsmo
Recent events (confirmed to have occurred)
- 12/12/2007: contract awarded for the Elwha Water Facilities (EWF); $69,649,900 to Watts/DelHur
- 09/07/2007: contract awarded for construction of the Port Angeles Water Treatment Plant (PAWTP); $24,482,750 to Watts/Korsmo